Legacy Pointe's developer has asked the city to change the rules for the 213-acre development north of Saturn Parkway, between The Crossings and Kedron Road. The request, PDA 2225-2026, would take the 300-room hotel out of the plan, add 330 apartments, allow a vehicle dealership and change several building design standards. The Planning Commission talked it over at a work session on Nov. 23, 2026 and is scheduled to hold a public hearing Dec. 14, 2026. The Board of Mayor and Aldermen (BOMA) would take it up Jan. 4 and Jan. 19, 2027.
The applicant is SouthStar LLC, the Brentwood developer behind Legacy Pointe. According to Senior Planner Gilles Morin's staff report, the request is "a revision to the Pattern Book that would include changes to the commercial development standards, project layout, and phasing." (The pattern book is the development's own rulebook.)
Proposed Legacy Pointe phasing plan showing phases 1A through 3 between The Crossings, Kedron Road and Saturn Parkway, with a summary of 568,985 square feet of commercial space, no hotel rooms and 1,589 homes.
Source: Proposed phasing plan, Legacy Pointe pattern book, Spring Hill Planning Commission work session packet, Nov. 23, 2026
What would change
Figures are from the Nov. 23 staff report and revised pattern book.
| Current plan (2025) | Proposed (2026) | |
|---|---|---|
| Hotel rooms | 300 | 0 |
| Pickleball courts | 12 | None listed |
| Active-adult homes | 205 | 0 |
| Townhomes (Phase 3B) | 50 | 0 |
| New apartments (Phase 2C) | — | 330 |
| Total homes | 1,514 | 1,589 |
| Total commercial space | 589,285 sq ft | 568,985 sq ft |
| Wholesale club phase | 246,000 sq ft, wholesale club plus retail and restaurants | 166,000 sq ft, wholesale club |
| Vehicle dealership with outdoor display | Not allowed | Allowed |
| Parking as a standalone use | Allowed | Removed |
| Blank wall facing a street | Up to 15 ft | Up to 25 ft (40 ft for buildings over 50,000 sq ft) |
| Ground-floor windows | At least 50% | At least 5% |
| Parking in front of buildings | Prohibited | Permitted |
| Secondary materials (corrugated metal, vinyl, T-111 plywood siding and others) | Up to 30% of a facade | Up to 50%, but not in the bottom 3 ft of street-facing walls |
| Recreational area | 17.39 acres | 16.0 acres |
| Estimated sewer demand | 418,582 gallons/day | 376,532 gallons/day |
| Estimated daily car trips (applicant's study) | 38,996 | 31,540 |
- Windows. The 50%-to-5% change is how staff summarized it. The pattern book already has a separate 5% rule for "heavy retail" buildings, and its examples include membership wholesale clubs. The new redline would apply the 5% figure to the general commercial and mixed-use standards as well.
- Materials. Staff says the cap on those materials "was originally limited to 20%, changed to 30%, and now proposed to be 50%." The redline also strikes "aluminum, steel, or other metal sidings" from the list of restricted materials.
- Sewer. Staff wrote that it "would like to verify these numbers with Spring Hill Water."
- Unchanged: "There are no proposed changes to the bulk standards," such as height and setbacks, staff wrote.
The packet doesn't name the wholesale club tenant. We reported in October that a Sam's Club real estate entity bought a 19-acre Legacy Pointe lot in January 2026.
How the plan got here
Aldermen first approved the development, then called Spring Hill Crossings, with Ordinance 22-24. It passed on second reading Dec. 19, 2022. That plan allowed a 136,000-square-foot U.S. Tennis Association (USTA) headquarters and tennis center, 600,000 square feet of commercial space, 1,000 hotel rooms and 2,130 homes. In May 2023, aldermen also approved a tax increment financing plan for the area (Resolution 23-89). It lets part of the site's new property taxes help pay for public improvements like roads, up to $55 million. The 2026 packet doesn't address it.
In March 2025, the USTA withdrew from the project. SouthStar President Glenn McGehee told WSMV it was "a tough fundraising environment." In June 2025, aldermen unanimously approved Ordinance 25-17. It removed the tennis center and added a "heavy retail" category. According to the May 2025 staff report, that change took the plan from 1,600 homes and 600 hotel rooms to 1,514 homes and 300 hotel rooms, and raised commercial space to about 589,000 square feet.
The site is graded, several internal roads are open, and "many commercial pads were finished but not yet under vertical construction," staff wrote.
What staff said
On uses, staff said it asked for standalone surface parking lots to be removed as a use "because standalone lots are an inefficient use of land," but said "the proposed Vehicle Dealership use is not ideal for the planned development."
On design, staff wrote: "The proposed design standards are significantly different than what was previously approved. Staff believe there could be an opportunity to compromise in a manner that does not lower the design standards."
On the new phasing, staff wrote: "for Legacy Pointe, many infrastructure improvements are tied to specific phases. Completely changing the phasing could result in a delay or missed benchmark in critical installment of infrastructure."
The packet doesn't include an applicant letter explaining the changes. The pattern book's "Benefits to the City" section projects about $8 million in impact fees (one-time fees developers pay toward infrastructure) and "over 2,600 jobs" at build-out.
What was said at the work session
There was no vote. Quotes below are from our own transcription of the city's video, which has no captions.
Houston McGehee of SouthStar called it "a text change to allow us to bring some of the retailers we're working with." He said "we're not asking to change any of the entitlements." Answering a question from Mayor Matt Fitterer, a member of the development team said demand over the past 18 months had been for "national tenants that have a regional draw," with design expectations "more in keeping with" The Crossings next door.
Chairman Elizabeth Droke said she "really didn't like the change from 50% to 5% on the ground floor transparency" and was "very much opposed to that change." Fitterer suggested tying the lower window and material rules to specific tenants or building sizes. The development team said it would come back with more specific language; "by no stretch are we trying to ask for 5%," one member said.
Alderman Jaimee Davis asked whether the city could get back the sewer capacity the new plan wouldn't need. The development team said it wanted to keep its current allocation for now because parts of the plan could still change. Another commissioner noted that "a zoning entitlement around sewer capacity is different from an allocation."
Vice Chairman Greg Groninger asked for the sewer and traffic estimates to be verified before the vote. He said a dealership "is going to increase auto traffic" and that he was "not thrilled about a car dealership." The development team said the dealership would replace about 100,000 square feet of planned office, with less sewer demand and fewer rush-hour trips. Commissioner Bob Moreo asked for details on how car-carrier trucks would load and unload.
Crossings Boulevard and Crossings Circle
The same night, the commission reviewed Resolution 26-102. It would reclassify Crossings Boulevard and Crossings Circle from arterial to collector roads on the city's Major Thoroughfare Plan map. Arterials are larger roads with wider right-of-way (95 feet versus 75) and different driveway rules. According to Associate Planner Benjamin Pavlic's memo, the plan's text already calls both roads collectors, but one map shows them as arterials. A former manager at the consultant that wrote the plan told staff the map "was colored in error." Both roads were designed to collector standards, and the Transportation Advisory Committee recommended the change Nov. 16, 2026.
At the work session, Fitterer said the classification "was not an error." In his words, "it was done intentionally to create enough ambiguity in it so that we could keep impact fees open as a funding mechanism," which he said is "no longer relevant since the road is built." The change would still go to BOMA.
What happens next
Staff told the applicant to address work-session comments by its Nov. 30 revision deadline. The public notice lists both items for:
- Planning Commission: Dec. 14, 2026, 5:30 p.m.
- BOMA: Jan. 4 and Jan. 19, 2027, 6 p.m.
All meetings are in the Board Room at City Hall, 199 Town Center Parkway. Under the commission's agenda rules, speakers on agenda items get five minutes after the staff report. If you can't attend, the city takes written comments at [email protected].