Updated Nov 10: Corrected two things. The city's July 2026 rate step did raise bills, and the Columbia pipeline now has an approved plan: see the rate numbers and the Columbia pipeline details under "When does it end" below. We also tightened the description of when the moratorium can end to match the state's order. More on bills, rates and the lawsuit in our water and sewer bill guide.

If you live in Spring Hill, the biggest thing happening in your city government is something most people have never heard of: since January 2026, the city has been under a sewer moratorium. New construction can't get sewer connections. Businesses that want to expand are being told no. Building permits are at what the city administrator calls "new lows."

Your toilet still flushes, and the moratorium itself hasn't changed your service. Your bill did go up this summer, but for a separate reason: a 30% step in water and sewer rates that took effect July 1 and first showed on the August bill, the last of three increases adopted in 2024. The water and sewer bill guide has the numbers. If you didn't go to council meetings, you could live here for a year and never know. But it touches almost everything the city decides right now, and it's worth understanding. To write this, I went through every board agenda packet and meeting recording from 2026 — the packets run a couple hundred pages a meeting. Here's the plain version, so you don't have to.

What the moratorium actually is

On January 5, 2026, the Board of Mayor and Aldermen passed Ordinance 25-29, which does three things:

  1. Freezes new sewer capacity. New development can't get sewer taps, which in practice means new subdivisions, new commercial buildings, and most expansions are on hold.
  2. Allows swaps. An existing building can change tenants or uses as long as the new use produces the same amount of wastewater or less. A retail space can become another retail space. It can't become a restaurant.
  3. Sets aside a reserve. The board kept 100,000 gallons per day of capacity that it can hand out at its own discretion, case by case. Ten months in, it has handed out 960 gallons a day of it, according to city staff: an endodontist office and a medical infusion center earlier in the year, and Nelly's Italian Cafe in October.

The city wrote these rules, but it didn't choose to have a moratorium. A consent order from the Tennessee Department of Environment and Conservation, signed in 2025 over problems at the city's wastewater treatment plant, requires the city to stop new sewer connections for projects that don't already have vested rights. Ordinance 25-29 is the city's framework for living within that order: who keeps their capacity, who waits, and how the reserve gets spent. The city says the moratorium stays in place until the plant meets the order's standards for 12 consecutive months. The order's own wording is more specific: it lasts until the city has gone 12 consecutive months without a reported bypass or a sewer overflow over 400 gallons, and TDEC rescinds or modifies it in writing. TDEC can also grant partial relief if the city reduces stormwater and groundwater getting into its sewer pipes or adds treatment capacity.

How it got to this point

Spring Hill's water reclamation plant sits on Mahlon Moore Road and treats the sewage for a city that roughly doubled in population in fifteen years. By 2025 the plant was in trouble: notices of violation from the state, nitrogen discharges far above permitted levels, broken solids-handling equipment, and wet-weather bypasses — times when partially treated water left the plant because it couldn't keep up.

In August 2025, the mayor and the city administrator held the first special work session on the TDEC consent order. The moratorium followed in January. In June 2026, the board declared a formal emergency at the plant and authorized hauling sludge away by truck because the plant couldn't dewater it on site.

The math behind the freeze is simple. The state says the plant can't reliably treat what it already receives. Every new tap adds flow. So the city stopped adding taps.

What it means in practice

For homeowners, almost nothing changes day to day. Existing homes keep their service. You can renovate, sell, and buy like normal.

For anyone trying to build or expand, it's a wall. The clearest example came at the board's August 17 meeting. Nelly's Italian Cafe — seventeen years in town, five to six hundred pizzas out the door on a Saturday — wanted to expand into the vacant tobacco shop next door and add seats. The city's design tables assign 35 gallons per day of sewer demand to every restaurant seat. More seats means more calculated flow, more calculated flow means the request fails the swap test, and staff recommended denial. Not because anyone thought Nelly's would actually overwhelm the plant — the engineering memo estimated the real increase at about 263 gallons a day, roughly what two households use — but because the ordinance scores requests on design tables, not water bills.

The board spent twenty minutes visibly straining against its own rule. It found a way through in the fall: a revised engineering memo that recalculated the expansion at 460 gallons a day using the city's own tables (down from 1,120), and a full ordinance amendment. Ordinance 26-17 granted Nelly's 460 gallons a day from the reserve, passing on final reading October 5. It takes two readings of a city ordinance to add some pizza seats, which tells you how carefully the board is rationing.

The moratorium also shows up in the city's books. Development fees have collapsed. Permits are at record lows. The city administrator has said he doesn't expect that to reverse for at least a couple of years. Growth was quietly paying a meaningful share of the city's bills, and the city has chosen to stop growing until the plant catches up. The freeze is also a likely reason the Sprouts announced for Duplex and Port Royal roads hasn't filed a site plan, though neither the developer nor the city has said so.

The part that's actually going well

Here's what surprised me reviewing the August 17 meeting: the plant itself is genuinely improving, faster than the city expected.

In April 2025 the plant was discharging about 95,000 pounds of nitrogen a month. By August 2026 it was at about 24,000, and there hadn't been a bypass since June 2, despite heavy rain events. New operational leadership and outside experts have the plant running close to its original design parameters for the first time in years.

That improvement had a concrete consequence at the same meeting: the board voted 9-0 to cancel the standalone $25–28 million centrifuge project that was supposed to fix the plant's solids problem. Staff's reasoning was that the project was designed three years ago, around assumptions of a poorly run plant, and a well-run plant doesn't need it — at least not in that form. Folding the work into the larger plant rebuild instead is expected to save $10–12 million. The city was clear that this does not delay the moratorium's timeline. It's a sign the crisis phase may be ending, not a sign the freeze is.

The number that explains why this will take years

The moratorium froze new commitments. It didn't erase the old ones — and the old ones are enormous.

In September 2025, the city compiled a list of every development it had already promised sewer connections to — "vested" projects, meaning they hold legal rights the city can't simply cancel. The document totals the outstanding commitments: 9,100 more homes, 13.7 million square feet of commercial space, and 1,498 hotel rooms, all promised connections to a plant the state says can't reliably treat what it already receives.

Some of the line items put the city's situation in sharp relief. June Lake still has 2,579 of its 2,926 homes to build, plus 3.9 million square feet of office — and this fall its homebuilder asked to keep building pipes at its own risk, with no sewer guaranteed (more on that below). Legacy Pointe's 1,600 homes and 600 hotel rooms haven't started at all. (Legacy Pointe's commercial side is moving: see Sam's Club in Spring Hill: the $11.3 million Legacy Pointe land deal and what's next.) Roughly 1,400 committed homes sit in projects listed with no activity whatsoever. Even a Whataburger and a Bruster's Ice Cream appear on the list — in the "vested projects expiring" column, which is its own quiet story about what the freeze does to smaller plans over time.

This list is why lifting the moratorium isn't just about fixing the plant. Every gallon of new capacity the city builds is already spoken for. The city's water team said as much at a June board meeting: the city "has already committed to more development capacity" than even the first round of the $320 million rebuild provides — "so we will be working for probably fifteen years straight to program things until we hopefully can get to a point where we feel like we've caught up."

When does it end

There's no announced end date. What exists instead is a set of milestones:

  • The Columbia connection. The nearest-term relief is a pipeline to Columbia. On Oct. 19, aldermen voted unanimously (Resolution 26-302) to proceed with an interlocal agreement. It would be a 12-inch sewer main from the plant on Mahlon Moore Road, along that road and then a TVA easement for several miles, to Columbia's system on its north side. The city puts the cost around $12 million, $9 million for the pipeline and $3 million for upgrades to the Carter's Creek Pike pump station, all paid by Spring Hill, plus a usage rate paid to Columbia. It would carry at least 500,000 gallons a day and up to 1.5 million. Columbia's council voted for it Oct. 8. The city gave no construction dates, and the moratorium stays in place until the order's conditions are met. When that pipe is wet, the capacity math changes.
  • The plant rebuild. The long-term fix is a roughly $320 million overhaul of the city's water and wastewater system — new reservoirs on 250 acres already purchased, a rebuilt treatment plant, and an advanced purification loop that would be the first of its kind in Tennessee. The city's target for final commissioning is May 27, 2030. The mayor keeps a countdown clock above his office door.
  • The consent order. Ultimately TDEC, not the city, decides when Spring Hill has fixed enough to be trusted with growth again. The order requires a written decision from the state, not just a clean year.

The honest reading: the freeze in something like its current form lasts years, not months. What may loosen sooner is the edges — the discretionary reserve, and possibly capacity clawed back from allocation holders who aren't using it. In August the board asked staff for a report on how allocated capacity is actually being used, with the stated possibility of reclaiming unused allocations for businesses that are ready to build now.

Where it stands in November

The board's November 2 meeting showed both edges of the freeze at once.

A dog daycare waits. Pooch Playhouse, an existing boarding and daycare business on Parkway Drive, asked for 2,680 gallons a day from the reserve to add kennels, grooming stations and staff. Its owner told the board it already runs near capacity, with a waiting list that sometimes reaches 40 dogs. City staff recommended drafting an agreement. Vice Mayor Trent Linville said he didn't think the ordinance gave the board authority to approve it, and the city attorney warned it could open the door to similar requests, WKRN reported. Alderman Scott Wernert compared dog boarding to childcare and leaned toward yes. The board gave no direction. The mayor asked for time to review the ordinance first, so the request is on hold.

Builders lay pipes they may never get to use. At the same meeting, the board backed two agreements that would let Signature Homes install water and sewer lines at June Lake, for the Windfall Phase 1 neighborhood and a 75-lot section that has sewer allocation for only 14 of its homes, entirely at its own risk. The pipes would be inspected and maintained but not connected. Ward 2 Alderman Jaimee Davis made sure everyone understood the city could decline to ever hook them up, and staff confirmed the builder knows that. Staff said other developers are asking to do the same. Because it was a discussion item, there was no vote; the agreements could come back for a vote on Nov. 16.

Put those together and you have the moratorium in one evening: a business already operating in town can't get 2,680 gallons, while a builder can bury pipe on the hope that someday the answer changes. Both outcomes follow the rules. Meanwhile, of the 100,000-gallon reserve, 99,040 gallons are still sitting there, guarded carefully.

What to watch next

  • Nov. 16: a possible board vote on the Signature Homes at-risk infrastructure agreements at June Lake.
  • Pooch Playhouse: whether the board decides the reserve can be used for an expansion like this one. Whatever it decides becomes the template for every small business that comes after.
  • The Columbia force main and plant upgrades: the milestones above are the ones that change the math. Everything else is rationing.

Related


This article draws on my review of 2026 BOMA agenda packets and meeting recordings, including the meetings of January 5, August 17 and November 2, the November 2 board packet, and the August 5 State of the City address. Figures are as stated by city officials in public meetings and documents. First published August 18, 2026; updated November 9, 2026 with the Nelly's decision and the November 2 meeting.